Re: [Tails-l10n] [Tails-dev] Release schedule for Tails 1.0.…

Delete this message

Reply to this message
Author: intrigeri
Date:  
To: Tails localization discussion
Subject: Re: [Tails-l10n] [Tails-dev] Release schedule for Tails 1.0.1 and 1.1
anonym wrote (29 May 2014 17:37:57 GMT) :
> For the non-Tails repos (Tails Greeter etc.) we have the problem that
> their release branches have Wheezy-migration stuff merged into them, and
> no branches with the last good state suitable for Squeeze has been
> restored yet. OTOH nothing has been added since since 1.0 that should be
> in 1.0.1 so I don't think this will be a problem unless some
> translations are still unfinished. Any ideas?


I say just keep these .deb's in 1.0.1 to the same state as in 1.0.

>> 2014-07-01 "Hard" feature freeze for 1.1.


> Once the "hard" freeze for 1.1 happens, translation work for 1.1 should
> be done in the *testing* branch in Tails' Git repo.


Given the huge amount of doc updates, maybe it would be good to start
translating stuff based on the testing branch earlier than the freeze,
no?

Cheers,
--
intrigeri
| GnuPG key @ https://gaffer.ptitcanardnoir.org/intrigeri/intrigeri.asc
| OTR fingerprint @ https://gaffer.ptitcanardnoir.org/intrigeri/otr.asc