As was decided during the last few days, Tails 1.1 will be postponed
[1]. Ignore the old release schedule for Tails 1.1 [2]!
Just to be clear, Tails 1.0.1 will be a point-release of 1.0 that's
still based on Debian Squeeze, and all the different 1.1 releases will
be based on Debian Wheezy.
Here's the release schedule (unless I've misunderstood or made a
mistake) for Tails 1.0.1 and 1.1:
2014-05-29 Test 1.1~beta1.
2014-05-30 Officially release 1.1~beta1.
2014-06-08 Firefox 24.6.0 ESR sources are available.
Package and upload Firefox 24.6.0 ESR.
Tag 1.0.1 in Git.
Start building and uploading 1.0.1 ISO/IUKs...
2014-06-09 Finish building by 12:00 (CEST)
Start testing Tails 1.0.1 at 12:00 (CEST)...
2014-06-10 ... and finish it by 12:00 (CEST) on the 10th.
Officially release Tails 1.0.1.
2014-06-10 The remaining features aimed for 1.1 should be "almost
done" at this point. This should leave some room for
additional round-trips that may be needed to get them
into a mergeable state.
2014-06-15 "Soft" feature freeze for 1.1; developers should act as
if this is the actual feature freeze for 1.1.
2014-06-16 *Maybe* publish a 1.1~beta2 ISO without any testing
beyond a run in the automated test suite.
2014-07-01 "Hard" feature freeze for 1.1.
Tag 1.1~rc1 in Git.
Build and upload 1.1~rc1 ISO.
2014-07-02 Testing Tails 1.1~rc1.
2014-07-03 Officially release Tails 1.1~rc1.
2014-07-20 Firefox 24.7.0 ESR sources are available.
Package and upload Firefox 24.7.0 ESR.
Tag 1.1 in Git.
Build and upload 1.1 ISO.
2014-07-21 Testing Tails 1.1.
2014-07-22 Officially release Tails 1.1.
Please let me know ASAP, intrigeri, if something in the above seems
incorrect! If you ACK it, I'll update the calendar.
Tails developers and contributors, are you available for testing on the
following dates?
* 2014-07-02 for 1.1~rc1
* 2014-07-21 for 1.1