> Here's the release schedule:
As you may have noticed, there's been a delaying of the next Firefox ESR
release for one week. So our own release agenda changed a bit
accordingly. It now is:
- 2016-11-11: all branches for 2.7 must be merged by 6pm CEST
- 2016-11-12/13: build and upload the ISO image
- 2016-11-13/14: test suite
- 2016-11-15: release
Usual testers, please let me know (privately) about your availability
for testing the ISO on:
- 2016-11-13: if I'm able to build and upload the ISO soonish, testing
it could start that day.
- 2016-11-14: all day
- 2016-11-15: until 6pm CEST, in case we did not complete the test
suite the day before
Note that I'll be travelling to the sprint on 2016-11-14, so testers
will have to self-organize a bit while I'm offline during that day.