Re: [Tails-dev] Release schedule for Tails 2.7

Üzenet törlése

Válasz az üzenetre
Szerző: bertagaz
Dátum:  
Címzett: tails-dev
Tárgy: Re: [Tails-dev] Release schedule for Tails 2.7
Hi,

On Mon, Oct 03, 2016 at 12:24:57PM +0200, bertagaz wrote:
>
> Here's the release schedule:


As you may have noticed, there's been a delaying of the next Firefox ESR
release for one week. So our own release agenda changed a bit
accordingly. It now is:

- 2016-11-11: all branches for 2.7 must be merged by 6pm CEST
- 2016-11-12/13: build and upload the ISO image
- 2016-11-13/14: test suite
- 2016-11-15: release

Usual testers, please let me know (privately) about your availability
for testing the ISO on:

  - 2016-11-13: if I'm able to build and upload the ISO soonish, testing
    it could start that day.
  - 2016-11-14: all day
  - 2016-11-15: until 6pm CEST, in case we did not complete the test
    suite the day before


Note that I'll be travelling to the sprint on 2016-11-14, so testers
will have to self-organize a bit while I'm offline during that day.

bert.