The next Firefox release is delayed by one week.
----- Forwarded message from Ritu Kothari <rkothari@???> -----
Date: Fri, 28 Oct 2016 17:34:04 -0700
From: Ritu Kothari <rkothari@???>
To: dev-platform@???, Firefox Dev <firefox-dev@???>
Subject: [desktop][mobile] Schedule Update for 50, ESR45.5 release and Merge day
Schedule change:
- 50 go-live date is Nov 15th (was Nov 8th).
- ESR 45.5 go-live date is Nov 15th (was Nov 8th).
- Merge day is Nov 14th (was Nov 7th).
- Beta 51 cycle starts ~Nov 16th
- Aurora 52 cycle starts ~Nov 18th.
- Beta -> Release migration is Oct 31st (remains unchanged).
- 50.1.0 (planned dot release) go-live date of Dec 13th remains
unchanged.
- 51 go-live date of Jan 24th remains unchanged.
*Why the change in schedule?*
- We decided to take two late uplifts (in m-b yesterday) re:add-on
SDK (bugs
1309351 and 1309350)
- These two changes need more bake time on Beta channel.
- RC mode for Fx50 starts on Oct 31st & we remain in code freeze mode
for two weeks.
- RC builds will be pushed out on an as-needed basis.
Please let me now if you have any questions or concerns.
Thanks,
Ritu