[Tails-dev] Release schedule for Tails 1.5

Supprimer ce message

Répondre à ce message
Auteur: intrigeri
Date:  
À: tails-dev
Nouveaux-sujets: Re: [Tails-dev] Release schedule for Tails 1.5
Sujet: [Tails-dev] Release schedule for Tails 1.5
Hi,

I'll be the release manager for the beginning of the Tails 1.5 cycle
(until August 4), and then anonym will take over.

Tails 1.5 is scheduled to be released on 2015-08-11. For the
list of tickets targeting Tails 1.5, have a look at:

https://labs.riseup.net/code/projects/tails/issues?query_id=182

Here's the preliminary release schedule:

* 2015-07-31:
  - Freeze Tails 1.5: all features targeting Tails 1.5 must be merged
    into the `devel` branch by noon CEST. This hopefully includes
    a Tor Browser candidate based on the latest Firefox 38 ESR.
  - Build and upload Tails 1.5~rc1


* 2015-08-01: Test and release Tails 1.5~rc1

* 2015-08-05: anonym becomes RM

* 2015-08-10:
   - All branches targeting Tails 1.5 must be merged into the `testing`
     branch by noon CEST.
   - Tor Browser 4.5.x, based on Firefox 38esr, is hopefully out so
     we can import it.
   - Build and upload Tails 1.5 ISO image and IUKs.
   - Start testing Tails 1.5 during late CEST if building the image
     went smoothly.


* 2015-08-11:
- Finish testing Tails 1.5 by the afternoon, CEST.
- Release Tails 1.5 during late CEST.


So, testers:

* please let me know if you are available on 2015-08-01

* please let anonym know if you are available on 2015-08-10 (late
evening, CEST) and/or 2015-08-11 (whole day)

Cheers!

--
intrigeri