Hi,

anonym wrote (29 May 2014 05:49:08 GMT) :
> 2014-07-03 Officially release Tails 1.1~rc1.


For the record, there will be a Wheezy point-release on July 12th.
Too bad we won't have it in the RC, but no big deal: I don't remember
a Debian stable point-release breaking anything for us.

(Did I mention that Debian is a rock-solid, robust basis, once
released, and that's one of the reasons why we ideally, we should fix
bugs in it before it's frozen? Oh yeah, I probably mentioned it a few
months before the Wheezy freeze. Well, Jessie will be frozen on the
5th of November.)

Cheers,
--
intrigeri
| GnuPG key @ https://gaffer.ptitcanardnoir.org/intrigeri/intrigeri.asc
| OTR fingerprint @ https://gaffer.ptitcanardnoir.org/intrigeri/otr.asc