Hi,

I'll be the RM for the Tails 0.20 release. Here's its preliminary
release schedule:

2013-07-30 freeze, build and upload Tails 0.20~rc1 ISO
2013-07-30 translation window starts
2013-07-31 test Tails 0.20~rc1
2013-08-01 release Tails 0.20~rc1

  2013-08-04   Firefox 17.0.8 ESR source is available
               => intrigeri packages it (right?)
  2013-08-06   Firefox 17.0.8 ESR is officially out
  2013-08-06   translation window ends
  2013-08-07   build and upload Tails 0.20 ISO
  2013-08-07   test Tails 0.20
  2013-08-09   release Tails 0.20