02/06/13 21:54, intrigeri wrote:
> Hi,
>
> intrigeri wrote (23 May 2013 22:00:53 GMT) :
>> Here's its preliminary release schedule:
>
>> 2013-06-15 freeze, build and upload Tails 0.19~rc1 ISO
>> 2013-06-16 test Tails 0.19~rc1
>> 2013-06-17 release Tails 0.19~rc1
> [...]
>> * Core developers: after a quick survey, we need one more person to
>> volunteer for the RC1 test suite day (June 16). Please volunteer
>> or make it clear that you can't make it. If we are not enough
>> volunteers, then I'll have to reschedule the whole thing, and I'd
>> rather do this sooner than later.
>
> There are not enough volunteers to "run" the RC1 test suite of
> June 16, so we have to reschedule a bit the RC1 planning (the final
> release timing is fine) -- I propose:
>
> 2013-06-13 freeze, build and upload Tails 0.19~rc1 ISO
> 2013-06-14 test Tails 0.19~rc1
> 2013-06-15 release Tails 0.19~rc1
>
> So, who's available to "run" the test suite on June 14?
I'll be available for running the complete automated test suite, and
I'll probably also have time to do some portion of the manual test suite.
Cheers!