Re: [Tails-dev] Tails 0.18 release schedule

Delete this message

Reply to this message
Autor: intrigeri
Data:  
A: The Tails public development discussion list
Assumpte: Re: [Tails-dev] Tails 0.18 release schedule
Hi,

intrigeri wrote (06 Apr 2013 10:11:34 GMT) :
> Here's the preliminary release schedule for Tails 0.18:


> 2013-05-03 freeze, build and upload Tails 0.18~rc1 ISO
> 2013-05-04 test Tails 0.18~rc1
> 2013-05-05 release Tails 0.18~rc1


> 2013-05-13 Firefox 17.0.6 ESR is out, let's package it
> 2013-05-14 build and upload Tails 0.18 ISO


Done, *but* that was just before I learnt of CVE-2013-2094.

So, I'm going to:

1. wait for a fixed kernel to land into wheezy-security
2. build and upload another 0.18 ISO (and maybe call it 0.18.1, I'm
not sure which one will lead to more confusion / for whom),
hopefully today or tomorrow

I expect the ISO to be available for testers tomorrow (2013-05-16)
around noon CEST or not too much later, so testing can be done on
Thursday 16 and Friday 17, and we should be able to release late on
Friday 17.

For the record, the initial plan was:

> 2013-05-15 test Tails 0.18
> 2013-05-16 release Tails 0.18


Cheers,
--
intrigeri
| GnuPG key @ https://gaffer.ptitcanardnoir.org/intrigeri/intrigeri.asc
| OTR fingerprint @ https://gaffer.ptitcanardnoir.org/intrigeri/otr.asc