On Wed, Sep 26, 2012 at 03:10:36PM +0200, anonym wrote:
> > To end with, given the amount of nice stuff we're currently merging
> > into devel, I'd be sad to see this wait until December before being
> > shipped to users, and I'm starting to wonder if we should not make the
> > next release a major one. That could be Tails 0.14. How crazy does
> > that sound?
>
> Not crazy at all.


I'm all in for a major release. I'd really like it to include
feature/multikernel, something that looks fairly doable.

> *If* we indeed choose to do this I suppose that would push the Tails
> 0.14 freeze date to the next Firefox ESR release date, which is October
> 9th (essentially two weeks from now), so:
>
> October 9th: 0.14 freeze + release of RC1.
> October 23th: ESR backport is (hopefully) available.
> October 25th: release of RC2.
> October 30th: release of 0.14.


Fine with me.

--
Ague