Hi Georg,

Georg Koppen:
> Don't wait on us here for Tor Browser 8.5. The current plan is to have
> the release, which is scheduled for March 19, be a "normal" 8.0.x
> release and getting 8.5 out end of March.
> However, this is mainly bound to having the Android part in shape in
> time, because 8.5 will be the first major release with Android
> support. Thus, it might happen that we need to postpone 8.5 a little
> further into April.


OK, thanks a lot for the update! I totally missed that but I have
quite some backlog reading to do on Tor Browser team meeting minutes.

I'll update our release schedule and other plans accordingly.
This relaxes me a bit regarding #27466, #26553, and #28044
(Tor bugs, not Tails tickets).

Does this mean that the first 8.5.x release that has *no*
corresponding 8.0.x will be the 2019-05-14 one?

> That said, also keep in mind that Pwn2Own will be between March 20-22
> and Firefox is one of the targets. The actual schedule of exploit
> attempts is usually revealed at the beginning of the week, so not sure
> yet when a potential emergency release would need to happen (if at all).


I wish Mozilla made it so they have a scheduled release *after*
Pwn2Own instead of a couple days before… anyway, thanks, that's
definitely something we should keep in mind. Added to our calendar and
to our checklist for building release management schedules, so we rely
a bit less on you to remind us of such important things :)